Project Update - January 19, 2018
Published on January 19, 2018
Trims
Completed:
- About 430 trims (29% of the project)
- Maintenance Districts: 2, 5, 6, 17, 25, 27, 28, 38, 39, 40
- Fairplains Cemetery
Working:
- Maintenance Districts: 1, 3, 34, 36, 37
- Riverside Park and Greenwood Cemetery as weather allows
Removals
Completed:
- About 480 removals (34% of the project)
- Maintenance Districts: 5, 6,10
- Ah-Nab-Awen, Briggs, Plaster Creek Family, Garfield, Lincoln, Dickinson, and Clemente Parks
- Oak Hill Cemetery North and Woodlawn Cemetery East
Working:
- Maintenance Districts: 0, 2, 3, 10, 17, 35
- Riverside Park and Mary Waters Park
- Oak Grove Cemetery
Stumps (from removals)
Completed:
- 12 stumps
- About 1% of project
- Dickinson, Ah-Nab-Awen, Briggs, and Plaster Creek Family Parks
Working (as weather allows):
- Maintenance District 5
- Lincoln Park
Other Stumps
Contract awarded to three companies and includes street locations throughout Grand Rapids.