Project Update - January 11, 2018
Published on January 11, 2018

Trims
Completed:
- About 27% of the project
- Maintenance Districts: 2, 5, 6, 17, 25, 28, 38, 39, 40
- Fairplains Cemetery
Working:
- Maintenance Districts: 1, 27, 34, 36, 37
- Riverside Park and Greenwood Cemetery as weather allows
Removals
Completed:
- About 28% of the removals
- Maintenance Districts: 5, 6
- Ah-Nab-Awen, Briggs, Plaster Creek Family, Garfield, Lincoln, Dickinson, and Clemente Parks
- Oak Hill Cemetery North and Woodlawn Cemetery East
Working:
- Maintenance Districts: 0, 2, 3, 10, 17, 35
- Riverside Park and Mary Waters Park
- Oak Grove Cemetery
Stumps (from removals)
Completed:
- 12 stumps
- About 1% of project
- Dickinson, Ah-Nab-Awen, Briggs, and Plaster Creek Family Parks
Working (as weather allows):
- Maintenance District 5
- Lincoln Park
Other Stumps
Contract awarded to three companies and includes street locations throughout Grand Rapids.