Create a Citizen Access account
We use a third party application called Citizen Access for our Demolition Permit applications. If you've never used Citizen Access, we recommend that you review how to create an account before starting your application.
Step 2.Review the requirements
We can only issue a Demolition Permit in these situations:
- Site plan for redevelopment has been approved by the Planning Department
- Notice to Repair or Demolish has been issued by Building Inspections or Code Compliance
- Court order requiring demolition
Step 3.Make sure you have time to apply
This application will take about 30 minutes once you've gathered the required information identified in the steps below.
Step 4.Make sure you have all the required information
During the application process you will need to upload the following attachments:
- Proof of insurance - general liability, auto, and workers compensation
- Performance guarantee (surety) - performance bond, letter of credit, or cashier's check
- For properties with more than one building, you must also submit a site plan.
Step 5.Have your credit/debit card ready
You'll need to enter your credit/debit card information to pay the permit fee. We accept Visa, MasterCard and Discover.
The demolition permit fee varies based on the type of structure. The Sewer Lateral Service Demo/Cap Off Inspection fee is included in the permit fee.
Step 6.Apply Online
Step 7.We'll review your application
Expect to hear from us within 1-2 business days. We'll email you to confirm receipt of your application. Keep in mind that you might need to revise your application or attachments if we notice any missing or incorrect information.
Step 8.What Happens Next
Once we accept your application, we'll notify the public utilities. You should also contact them directly to request utility cut-off.
We need confirmation of gas, electric, and water utility cut-off before we can issue a Demolition Permit. Typically, the utility companies provide this to us. If you receive a utility cut-off notification, forward it to devcenter@grcity.us. We can't issue permits without these confirmations.